48 Electric LLC: 2 Megawatt Build-Out in a Live Data Center Environment.

2 Megawatt Build-Out

  • 2-megawatt build-out in a live data center environment.
  • Installed 15,000 feet of 300 KCMil
  • Installation of Busway, Feeder Cable Tie-ins to PDU, Tap boxes, Full commissioning.

LOCATION

  • Chandler, AZ

CONSTRUCTION DURATION

  • 2 Months